Menindee Lakes flood review

About

WaterNSW has reviewed its Menindee Lakes flood operations during the Darling-Baaka River flooding events between May 2022 and February 2023.

The review, conducted by WaterNSW and independently peer-reviewed, covered flood operations over three periods of intense flooding:

  • May to August 2022 - when flows at the Menindee town gauge exceeded the minor level.
  • September to November 2022 - when flows at Menindee town gauge exceeded the moderate flood level.
  • December 2022 to February 2023 - during which flows at the Menindee town gauge exceeded the major flood level from 30 December 2022.

The review made five findings and three recommendations, all of which have been accepted by WaterNSW.

The review found WaterNSW’s actions contributed to reducing overall flow peaks downstream of the lakes by 29.2%, supported by an appropriate set of policies and procedures, as well as identifying key areas for improvement, including upgrades to the river gauging network and community communication and engagement.

Background

The flooding events on the Darling-Baaka River between May 2022 and February 2023 were significant in their scale.

  • In 2022 more than 10,000 gigalitres of water reached the Menindee Lakes system – this is six times the lakes’ capacity and more than five times what would normally be received in a year.
  • There was a minor or greater flooding alert in place in Menindee for nine months – from June 2022 to February 2023.
  • Over that time, more than 8,000 GL was released from the lakes.

WaterNSW operates the Menindee Lakes system under agreed operating rules, including preservation of dam safety, conservation of water resources, and provision of flood mitigation where possible.

The flood review’s recommendations will be implemented alongside those endorsed by the NSW Government following its 2022 NSW Flood Inquiry, and the Office of the Chief Scientist and Engineer's Independent Review into the Menindee mass fish death event.

WaterNSW thanks the Menindee community for their input and observations, which helped inform the review, and looks forward to implementing measures to improve its performance for future flood events.

Read the review

Q&As

Why did WaterNSW review this event?

WaterNSW routinely conducts a review of major flood operations and other incidents to ensure procedures are followed and to identify opportunities for improvement.

What did the review cover?

The review was initiated to understand:

  • Whether WaterNSW systems, policies and procedures enabled WaterNSW to properly execute its functions over the course of the event.
  • Whether WaterNSW actions helped to provide flood mitigation benefits for the local area.
  • The quality and availability of inflow data and modelling, in particular, the inflows from unregulated tributaries.
  • The effectiveness of WaterNSW’s engagement and communications with other agencies involved in the emergency response; and
  • Opportunities to further enhance communications with the local community before and during the event.

Was the community consulted?

The review incorporates input from the community and WaterNSW customers.

Our review included feedback from local stakeholders. For example in late June 2023 WaterNSW held community drop-in sessions in Menindee over two days to gather feedback, and continues to engage with the Menindee community.  Feedback was also collected from WaterNSW’s Customer Advisory Group.

Why was the report delayed?

We had a huge amount of data over many months to analyse and that took us some time - probably a bit longer than we might have liked, but we’re pleased to make the report public now.

We also had the report independently assessed by an external expert, and built in time for that.

Isn’t this marking your own homework?

WaterNSW routinely conducts a review of major flood operations and other incidents to ensure procedures are followed and to identify opportunities for improvement. Continued improvement is very important to us. It was also important that this report was subject to an independent expert peer review.

Was the report independently assessed?

While the review itself was undertaken by WaterNSW, it was subject to an independent expert peer review before any recommendations were considered by the WaterNSW Board. Those findings are now publicly available.

Were external agencies involved?

The report was an internal WaterNSW review of our flood operations at Menindee Lakes.  We meet regularly with other agencies and some of the thinking from those discussions and feedback has been taken into account.

Is the WaterNSW gauging network sufficient to manage floods?

The review found there is an opportunity to improve the availability of streamflow data upstream of the lakes.

The number and location of river gauges created challenges for WaterNSW flood planning and operations during the flooding events, and a review of the gauging network is recommended.

We found that there were gaps in river data and information that would have been helpful during the floods.

Did WaterNSW underestimate flows from the Talyawalka?

Historical reports and analysis indicate that during past floods, inflows to Lake Wetherell have peaked at around 60% of the combined flows in the Main Channel at Wilcannia and the Talyawalka gauge at the Barrier Highway.

During the 2002-23 Darling River floods the combined gauges represented approximately 100% of the flows, far exceeding the previous expected ratio of 60% of the Wilcannia total flow peak.

While manual monitoring also took place (i.e. attending a site in person and performing a remote gauge reading), the widespread flooding made accessing some locations impossible.

The current design of the gauging network and subsequent uncertainties in assessing Menindee Lakes inflows had a bearing on the inflow modelling undertaken by WaterNSW.

What does this review say about fish deaths?

The review does not cover the March 2023 fish death event, but rather the flooding that preceded it. The fish death event was comprehensively reviewed by the Office of the Chief Scientist and Engineer. WaterNSW’s submission to that Review is available on the Chief Scientist and Engineer website.

What are the next steps?

Following discussion (and feedback) on the report with Government agencies and the community, WaterNSW will work to implement the listed recommendations as soon as possible.

Go to top

WaterNSW acknowledges the traditional custodians of the lands and waters on which we work and pay our respects to all elders past, present and emerging. Learn more