The Northern NSW Coatings Program will identify WaterNSW’s weirs throughout Northern NSW to receive essential maintenance work, including protective coating
Coating work will remove the risk of deterioration of essential WaterNSW assets and improve the structure’s resilience to environmental factors, extending their life by up to 25 years. This will enable WaterNSW to provide continued service to customers.
Keepit Dam spillway gates, Namoi Valley
Work to apply a protective coating on the surface of two spillway gates at Keepit Dam was carried out between 1 July 2024 and 28 February 2025.
Gunidgera weir gates, Namoi River
Work to apply a protective coating to Gunidgera weir gates, Namoi River, was carried out between 15 June 2023 and August 2023.
To minimise impacts to the community and customers, work was completed outside the irrigation season.
Tareelaroi regulator gates, Gwydir River
Work to apply a protective coating on the surface of Tareelaroi regulator gates, Gwydir River, was carried out between Monday 3 April 2023 and Friday 12 May 2023.
To minimise impacts to the community and customers, work was completed outside the irrigation.