Keepit upgrade

Keepit upgrade

Keepit Dam

  • Keepit Dam from airLocated on the Namoi River, 30km upstream of Gunnedah    
  • Dam completed in 1960    
  • Storage capacity of 425,510 megalitres    

About the upgrade

  • Cost: in excess of $100 million    
  • Funded by: the NSW Government    

Description

The Keepit Dam Upgrade is scheduled to begin construction works in April 2017. For safety reasons, public access to the main wall will not be permitted during the construction period, however a viewing and turning area will be available at the approach to the main wall. The access restrictions will commence from Thursday 23 March 2017, and continue until mid-2019. WaterNSW apologises for any inconvenience to the public caused during this period.

Upgrade to comply with ANCOLD and contemporary safety standards. Construct two spillways, three saddle dams and works to the main dam wall. Storage capacity and water releases will not be altered by the upgrade.

Benefits

  • Improved ability of dam to withstand extreme floods and earthquakes    
  • Stimulating local economy during construction    
  • Increased sustainable regional development    
  • Improved environmental outcomes through implementation of a biodiversity offset plan    

Milestones

Construction of two spillways (work package one)

  • 2009 August - Completion of design    
  • 2010 March - Commence construction    
  • 2011 September - Complete construction    

Dam wall modifications (work package two)

  • 2010 - Design completed    
  • 2014 - Commence electrical relocation    
  • 2015 - Complete electrical relocation    
  • 2016 - Commence post-tensioning    
  • 2019 - Complete post-tensioing    
  • Possible further works to follow post-tensioning    

Updates

  • 2017 March - Public access to the dam wall not permitted in preparation for construction works starting in April    
  • 2016 November - Tender awarded for construction works to strengthen dam wall    
  • 2016 March - Tenders for dam wall post-tensioning let to select group following EOI process    
  • 2014 December - Preliminary electrical works complete    
  • 2014 July - Preliminary electrical works 50% complete    
  • 2014 January - Tender awarded for preliminary electrical works    
  • 2013 April - Tender awarded to remove right abutment cofferdam    
  • 2011 October - Works package one completed    
  • 2011 June - Road base material donated to Lake Keepit Soaring Club    
  • 2011 February - New amenities handed back to Keepit State Park    
  • The Community Construction Liaison Group meeting regularly throughout the project for updates    
  • Construction progressing according to schedule    
  • 2010 March - Construction commences    
  • 2010 January - NSW Government announces funding for upgrade    

Fact sheets

Photos

Media releases

Contact

Project Manager: Nava Jeyachandran
Phone: 1300 662 077

Send us your inquiry